This works instruction describes the procedures to be followed during the different stages involved in treatment of timber with TOPRO 94 borate wood preservative solutions when using the immersion (dip diffusion) method.
| 2. |
OPERATING PROCEDURE FOR SOLUTION MIXING AND TRANSFER |
| 2.1 |
Ensure that all valves are closed. |
| 2.2 |
Add water to mixing/storage tank to ± 60% of the total
working solution volume required.
Note: A sufficient volume of working solution
should be prepared to ensure adequate overflow to the measuring
tank, i.e. at least 50 percent of the measuring tank volume capacity. |
| 2.3 |
Heat water in mixing/storage tank to ± 60°C and start
mixer. |
| 2.4 |
Slowly add the required mass of TOPRO 94 to the water in mixing/storage
tank and continue mixing and heating until all salts have dissolved. |
| 2.5 |
Stop mixer and add more water up to the required volume in mixing/storage
tank to ensure that the required mass concentration in grams of boric
acid equivalent (b.a.e) per litre of solution is obtained. |
| 2.6 |
Start mixer and mix for a further 5 minutes an ensure solution
temperature is maintained at ± 50°C. |
| 2.7 |
Draw a solution sample and determine b.a.e. mass concentration
by the hydrometer method. (See timber treatment manual, Works Instruction
No. TL/W06) |
| 2.8 |
Adjust solution mass concentration if necessary. (See timber treatment
manual, Works Instruction No. TL/W07). |
| 2.9 |
Open valve 1 and allow working solution to overflow from mixing/storage
tank to measuring tank. (Level in sight glass on measuring tank should
indicate at least 50 percent of the volume capacity. If not, prepare
additional working solution). |
| 3. |
OPERATING PROCEDURES DURING TREATMENT |
| 3.1 |
Solution transfer to dip tank |
| 3.1.1 |
Determine charge volume to be treated and fill in
a treatment charge sheet (Report Form No. TL/R11). |
| 3.1.2 |
Place timber to be treated in dip tank, and weigh
down. |
| 3.1.3 |
Record starting level in measuring tank after overflow
from mixing/storage tank has stopped (Report Form No. TL/R11). |
| 3.1.4 |
Open valve 2 and empty contents of measuring tank
into dip tank by gravity feed. |
| 3.1.5 |
Close valve 2. |
| 3.1.6 |
Open valve 3 and transfer working solution from mixing/storage
tank by gravity feed into dip tank to the required volume and start
dip tank heating to maintain solution temperature at 50°C, ±
5°C. |
| 3.1.7 |
Close valve 3 and proceed with dip treatment process.
Keep timber completely submersed from the entire dip treatment period
required. |
| 3.2 |
Solution transfer to mixing/storage tank |
| 3.2.1 |
On completion of dip treatment cycle, open valves
4 and 5, start transfer pump and transfer solution from dip tank to
mixing/storage tank. |
| 3.2.2 |
When dip tank is empty, close valves 4 and 5 and stop
transfer pump. |
| 3.2.3 |
Allow overflow from mixing/storage tank to settle and
record final level in measuring tank (Report Form No. TL/R11). |
| 3.2.4 |
Complete treatment charge sheet and accept or retreat
charge. |
| 3.2.5 |
Open valve 2 and empty contents of measuring tank
into dip tank. |
| 3.2.6 |
Close valves 1 and 2, open valves 4 and 5, start transfer
pump and transfer solution from dip tank to mixing/storage tank. Close
valves 4 and 5 and stop transfer pump. |
| 3.2.7 |
Remove treated timber from dip tank, spray with anti-sapstain/mould
solution and place in diffusion storage under complete cover. |
| 3.2.8 |
Prepare new charge and repeat steps 3.1.1 through
to 3.2.7.
Note:
1. Always ensure that working solution is well mixed and maintained
at
± 50°C before treatment of a new charge.
2. Determine the solution b.a.e. mass concentration by the
hydrometer
method before treatment of a new charge. (See timber treatment
manual, Works Instruction No. TL/W06).
|
| 4. |
OPERATING PROCEDURE FOR SOLUTION STORAGE |
| 4.1 |
4.1 Transfer all working solution from measuring tank
and dip tank to mixing/storage tank. (See steps 3.2.5 and 3.2.6) |
| 4.2 |
Open valves 6 and 7 (ensure that rinse tank is filled
with clean water). |
| 4.3 |
Start transfer pump and flush pump system with
clean water from rinse tank for at least 5 minutes. Close valves
6 and 7 and stop transfer pump.
Note: Flush water should be re-used for solution
mixing. |
| 5. |
OPERATING PROCEDURE FOR STRAT-UP AFTER EXTENDED
SOLUTION STORAGE |
| 5.1 |
Ensure that all valves remain closed. |
| 5.2 |
Heat mixing/storage tank contents to at least 60°C. |
| 5.3 |
Start mixer and continue mixing and heating at ±
60C until all salts and/or lumps have dissolved. |
| 5.4 |
Rectify working solution concentration if necessary.
(See steps 2.7 and 2.8) |
| 5.5 |
Continue treatment as described under section 3. |